摘要:
大型复杂装备研制项目高风险与参研单位多的特点使得研制过程中风险传导时有发生。针对风险传导要素风险源的识别问题,提出了一种基于关联规则(AR)与决策实验室分析法(DEMATEL)的风险源识别方法。该方法从数据挖掘的角度,先求解出风险类型与风险因素的关联规则,再求解出风险源之间的影响程度,最后通过DEMATEL得到各风险源相关参数。并且对某参研单位数据库中某阶段的数据用此方法完成了风险源的识别,识别结果显示了各风险类型对应的风险源以及易导致研制项目发生风险传导的风险源。
Abstract:Complex equipment development project characters of high risk and many research units result in risk transmission in the development process. To solve the risk source identification problem, a risk source identification method was proposed based on association rule (AR) and decision making trial and evaluation laboratory (DEMATEL). The association rules between risk type and risk factors were solved firstly, and then the interaction of the risk sources was obtained, both with data mining method. Finally, each risk source's relevant parameters were obtained through DEMATEL. Besides, a case was analyzed and the risk sources identification was completed by AR-DEMATLE method on a stage of the data stored in the database of a research unit. The identification result shows that the risk sources corresponding to various risk types and the risk sources leading to risk transmission easily.
-
表 1 风险类型与风险因素的关系(a)
Table 1. Relationship between risk type and risk factor (a)
风险因素 风险类型 B1 … Bm An B2 B3 … A2 B1 B3 A1 … … 表 2 风险类型与风险因素的关系(b)
Table 2. Relationship between risk type and risk factor (b)
风险因素 风险类型 B1 An An Bm An 表 3 风险源
Table 3. Risk source
风险类型 研发风险 质量风险 服务风险 风险源 技术
工艺
标准化
人员素质
设计更改技术
工艺原材料价格
拖期交付
退货返修
响应不及时表 4 风险源相关系数矩阵C
Table 4. Risk source correlation coefficient matrix C
风险源 C B1 B2 B3 B5 B7 B8 B12 B13 B14 B1 1 0.23 0.36 0 0.19 0 0.24 0.43 0.01 B2 0.21 1 0.32 0 0.27 0 0.04 0.12 0.01 B3 0.02 0.02 1 0 0.18 0.12 0.01 0.01 0 B5 0.37 0.29 0.06 1 0.22 0 0.02 0.02 0.30 B7 0.34 0.13 0.04 0 1 0 0.41 0.03 0.03 B8 0.02 0.01 0.01 0 0.05 1 0.03 0.01 0.02 B12 0 0 0 0 0 0.02 1 0.02 0.22 B13 0.16 0.17 0 0 0.05 0.04 0.39 1 0.25 B14 0 0 0 0.01 0.01 0.02 0.05 0.01 1 表 5 风险源综合影响矩阵T
Table 5. Risk source comprehensive influence matrix T
风险源 T B1 B2 B3 B5 B7 B8 B12 B13 B14 B1 0.64 0.50 0.62 0.01 0.59 0.17 0.97 0.59 0.53 B2 0.52 0.44 0.53 0 0.52 0.14 0.75 0.45 0.37 B3 0.17 0.13 0.21 0 0.19 0.08 0.26 0.13 0.12 B5 0.76 0.60 0.70 0.08 0.71 0.17 1 0.62 0.58 B7 0.47 0.36 0.43 0 0.46 0.11 0.74 0.40 0.39 B8 0.07 0.05 0.06 0 0.07 0.09 0.11 0.06 0.06 B12 0.02 0.01 0.01 0 0.02 0.02 0.11 0.02 0.10 B13 0.33 0.28 0.30 0.01 0.30 0.10 0.59 0.35 0.38 B14 0.02 0.02 0.02 0 0.02 0.01 0.05 0.02 0.10 表 6 DEMATEL方法计算结果
Table 6. Computational results of DEMATEL method
风险源 影响度 被影响度 中心度 原因度 中心度排序 属性 B1 4.62 3.01 7.63 1.61 1 原因因素 B2 3.74 2.41 6.15 1.33 3 原因因素 B3 1.29 2.90 4.19 -1.71 7 结果因素 B5 5.24 0.11 5.35 5.13 4 原因因素 B7 3.38 2.90 6.28 0.48 2 原因因素 B8 0.57 0.89 1.46 -0.32 9 结果因素 B12 0.32 4.58 4.90 -4.26 6 结果因素 B13 2.66 2.65 5.31 0.01 5 原因因素 B14 0.28 2.65 2.83 -2.37 8 结果因素 -
[1] 王飞, 魏法杰.大型复杂装备研发成本控制专家系统[J].北京航空航天大学学报, 2010, 36(4):490-494. http://bhxb.buaa.edu.cn/CN/abstract/abstract8487.shtmlWANG F, WEI F J.Expert system on cost control for complex equipment[J].Journal of Beijing University of Aeronautics and Astronautics, 2010, 36(4):490-494(in Chinese). http://bhxb.buaa.edu.cn/CN/abstract/abstract8487.shtml [2] MOEHRLE M G, WALTER L.Risk and uncertainty in R&D management[J].R&D Management, 2008, 38(5):449-451. doi: 10.1111/j.1467-9310.2008.00536.x/full [3] 王元明.工程项目供应链风险传递[M].北京:中国电力出版社, 2012:18-20.WANG Y M.Supply chain risk transmission in engineering project[M].Beijing:China Electric Power Press, 2012:18-20(in Chinese). [4] 郭波, 龚时雨, 谭云涛.项目风险管理[M].北京:电子工业出版社, 2012:24-29.GUO B, GONG S Y, TAN Y T.Project risk management[M]. Beijing:Publishing House of Electronic Idustry, 2012:24-29 (in Chinese). [5] 李勘.武器装备研制项目风险管理研究[M].北京:国防工业出版, 2011:76-99.LI K.Research on risk management of weapon equipment development project[M].Beijing:National Defense Industry Press, 2011:76-99(in Chinese). [6] RAFETERY J.Risk analysis in project management[M].London:E&FN Spon, 1994:40-60. [7] CARR M J, KONDA S L, MONARCH I, et al.Taxonomy-based risk identification[R].Pittsburgh, PA:Carnegie-Mellon University, 1993:7-12. doi: 10.1007/978-3-540-68255-4_20 [8] 任南, 韩冰洁, 何彦昕.基于WBS-RBS-DSM的项目风险识别与评估[J].系统工程, 2014, 32(11):96-100. doi: 10.3969/j.issn.1001-2362.2014.11.064REN N, HAN B J, HE Y X.Project risk identification and assessment based on WBS-RBS-DSM[J].Systems Engieering, 2014, 32(11):96-100(in Chinese). doi: 10.3969/j.issn.1001-2362.2014.11.064 [9] 王中原, 魏法杰.基于IFAHP—DEMATEL的军工企业法律风险识别研究[J].管理评论, 2015, 27(6):68-77. http://www.cnki.com.cn/Article/CJFDTOTAL-ZWGD201506008.htmWANG Z Y, WEI F J.An analysis of identification of the legal risk in military enterprises based on IFAHP and DEMATEL[J].Management Review, 2015, 27(6):68-77(in Chinese). http://www.cnki.com.cn/Article/CJFDTOTAL-ZWGD201506008.htm [10] 张子剑. 复杂装备研制风险管理研究[D]. 天津: 天津大学, 2007: 49-72. http://cdmd.cnki.com.cn/Article/CDMD-10056-2009071271.htmZHANG Z J.Research on risk management of the development of the complex equipment[D].Tianjin:Tianjin University, 2007: 49-72(in Chinese). http://cdmd.cnki.com.cn/Article/CDMD-10056-2009071271.htm [11] 许聪睿. 某型号雷达导引头研制项目风险识别与评估方法研究[D]. 北京: 中国科学院大学, 2015: 29-49. http://cdmd.cnki.com.cn/Article/CDMD-80090-1016003233.htmXU C R.Risk identification and evaluation methods research of a type of radar development project[D].Beijing:University of Chinese Academy of Sciences, 2015:29-49(in Chinese). http://cdmd.cnki.com.cn/Article/CDMD-80090-1016003233.htm [12] 周平, 姜寿山.航空产品研制项目的风险识别特征—因子建模技术研究[J].计算机集成制造系统, 2003, 9(7):542-545. http://www.cnki.com.cn/Article/CJFDTOTAL-JSJJ200307008.htmZHOU P, JIANG S S.Feature—Factor modeling of risk identification for aviation product development project[J].Computer Integrated Manufacturing Systems, 2003, 9(7):542-545(in Chinese). http://www.cnki.com.cn/Article/CJFDTOTAL-JSJJ200307008.htm [13] HAIMES Y Y, LAMBERT J, LI D, et al.Hierarchical holographic modeling for risk identification in complex systems[C]//Proceedings of the IEEE International Conference on System, Man and Cybernetics.Piscataway, NJ:IEEE Press, 1995, 2:1027-1032. [14] NGUYEN D, NGUYEN L T T, VO B, et al.A novel method for constrained class association rule mining[J].Information Sciences, 2015, 320(1):107-125. http://www.sciencedirect.com/science/article/pii/S0020025515003643 [15] VERYKIOS V S, PONTIKAKIS E D, THEODORIDIS Y, et al.Efficient algorithms for distortion and blocking techniques in association rule hiding[J].Distributed and Parallel Databases, 2007, 22(1):85-104. doi: 10.1007/s10619-007-7013-0 [16] 王瑛, 汪送, 管明露.复杂系统风险传递与控制[M].北京:国防工业出版社, 2015:38-41.WANG Y, WANG S, GUAN M L.Risk transmission and risk control for complex systems[M].Beijing:National Defense Industry Press, 2015:38-41(in Chinese).