Schedule planning method based on process modeling
-
摘要: 为了降低大型项目进度计划的复杂性,提出一种基于过程建模的项目进度计划方法.首先分析过程模型与项目进度计划之间的内在联系,给出VPML过程模型和甘特图的概念对应关系,为过程模型与项目进度计划的自动转换提供基本规则.特别针对大型项目中常见的"返工"现象,提出一种循环活动的线性化算法.该算法通过引入学习曲线的概念,模拟时间成本在重复工作中呈现出的学习效应,使时间进度的估算值更贴近真实情况.Abstract: To make the complexity of the schedule planning for large project lower, a new method was proposed to make project schedule plan based on process modeling. After analyzing the interrelationships between process model and project schedule plan, the concept mapping rules between them were presented to implement automate conversion between process model and project schedule plan. Because "redo" often occurs in large project that make schedule planning difficult, a repetition tasks linearization algorithm was proposed. The algorithm introduced learning curve concept to simulate the learning effect in repetition tasks in order to make schedule plan more precise than that of before.
-
Key words:
- process engineering /
- project management /
- process model /
- VPML /
- schedule planning
-
[1] 李铭, 刘超. 软件项目计划制定和追踪方法[J]. 计算机工程与应用, 2002, 22:157-158 Li Ming, Liu Chao.An approach of software project plan making and tracking [J]. Computer Engineering and Applications, 2002, 22:157-158 (in Chinese) [2] 李清, 陈禹六, 王青. 过程与项目管理方法的信息映射与集成[J]. 计算机集成制造系统-CIMS, 2001, 7:25-30 Li Qing, Chen Yuliu, Wang Qing. Information mapping and integration between process modeling and project management[J]. Computer Integrated Manufacturing Systems, 2001, 7:25-30 (in Chinese) [3] 王吉年, 张莉. 企业过程建模与项目管理及产品数据管理的集成[J]. 计算机工程与应用, 2003,39(30):206-208 Wang Jinian, Zhang Li. Integration of enterprise modeling, project management and produce data management[J]. Computer Engineering and Applications, 2003, 39(30):206-208 (in Chinese) [4] Lawrance M L Chung, Keith C C Chan. Integrating project planning and process modeling for software development Application-Specific Systems and Software Engineering and Technology. Richardson:USA, 1999:276-279 [5] 李丽萍, 李原, 韩毅, 等. IDEF3与甘特网络图相结合的进度计划方法[J]. 计算机集成制造系统-CIMS, 2004, 6:657-661 Li Liping, Li Yuan, Han Yi, et al. Method combining IDEF3 with gantt chart for schedule planning[J]. Computer Integrated Manufacturing Systems, 2004,6:657-661 (in Chinese) [6] 周伯生, 张社英. 可视化的过程建模语言VPML[J]. 软件学报,1997,8(增刊):535-545 Zhou Bosheng, Zhang Sheying. Visual process modeling language VPML [J]. Software Journal, 1997,8(supplyment):657-661 (in Chinese) [7] Project Management Institute. A guide to the project management body of knowledge [M]. Project Management Institute, 2004 [8] 张莉,周伯生,崔德刚,等.飞机全生命期过程建模技术及支持环境[J]. 北京航空航天大学学报,2001, 27(4):417-420 Zhang Li, Zhou Bosheng, Cui Degang, et al. Aircraft lifecycle process modeling technology and its supporting system [J]. Journal of Beijing University of Aeronautics and Astronautics, 2001, 27(4):417-420 (in Chinese) [9] 张莉, 王文. 大型过程的Import/Export解决方案[J]. 计算机工程与应用 ,2001,12:23-26 Zhang Li, Wang Wen. A solution on large process modeling by import/export technology[J]. Computer Engineering and Applications, 2001, 12:23-26 (in Chinese) [10] 张莉, 刘孟诏, 崔德刚. 飞机全生命期过程建模方法与技术[J].飞机设计,2001,3:1-5 Zhang Li, Liu Mengzhao, Cui Degang. The all life-cycle process modelling method and technique for aircraft[J]. Aircraft Design, 2001, 3:1-5 ( in Chinese) [11] Adedeji B Badiru, P Simin Pulat. Comprehensive project management[M]. Prentice Hall PTR, 2003
点击查看大图
计量
- 文章访问数: 2828
- HTML全文浏览量: 210
- PDF下载量: 1203
- 被引次数: 0